Consider the following six processes each having its own unique processing time and arrival time. Processes Arrival time Processing time P1 0 8 P2 0…
Consider the following six processes each having its own unique processing time and arrival time.
| Processes | Arrival time | Processing time |
| P1 | 0 | 8 |
| P2 | 0 | 4 |
| P3 | 0 | 5 |
| P4 | 1 | 9 |
| P5 | 1 | 7 |
| P6 | 0 | 1 |
Find average turnaround time using shortest job first scheduling algorithm.
From the BIWTA Assistant Engineer (CSE) February 2023 – Written (BUET) exam, question 9 of 9.